Document/ExhibitDescriptionPagesSize
1: 10-K Annual Report HTML 1.00M
2: EX-4.23 Instrument Defining the Rights of Security Holders HTML 815K
3: EX-4.25 Instrument Defining the Rights of Security Holders HTML 852K
4: EX-4.27 Instrument Defining the Rights of Security Holders HTML 97K
5: EX-4.29 Instrument Defining the Rights of Security Holders HTML 92K
6: EX-4.31 Instrument Defining the Rights of Security Holders HTML 92K
7: EX-10.33 Material Contract HTML 89K
8: EX-31.1 Certification -- §302 - SOA'02 HTML 28K
9: EX-31.2 Certification -- §302 - SOA'02 HTML 28K
10: EX-32.1 Certification -- §906 - SOA'02 HTML 25K
11: EX-32.2 Certification -- §906 - SOA'02 HTML 25K
17: R1 Document and Entity Information HTML 85K
18: R2 Audit Information HTML 29K
19: R3 Statements of Income HTML 100K
20: R4 Balance Sheets HTML 116K
21: R5 Statements of Member's Equity HTML 47K
22: R6 Statements of Cash Flows HTML 116K
23: R7 Organization and Nature of Operations HTML 27K
24: R8 Summary of Significant Accounting Policies HTML 58K
25: R9 Restricted Cash and Cash Equivalents HTML 27K
26: R10 Accounts and Other Receivables, Net of Current HTML 32K
Expected Credit Losses
27: R11 Inventory HTML 33K
28: R12 Property, Plant and Equipment, Net of Accumulated HTML 51K
Depreciation
29: R13 Derivative Instruments HTML 108K
30: R14 Other Non-Current Assets, Net HTML 35K
31: R15 Accrued Liabilities HTML 34K
32: R16 Debt HTML 88K
33: R17 Revenues from Contracts with Customers HTML 74K
34: R18 Related Party Transactions HTML 89K
35: R19 Commitments and Contingencies HTML 42K
36: R20 Customer Concentration HTML 56K
37: R21 Supplemental Cash Flow Information HTML 34K
38: R22 Summary of Significant Accounting Policies HTML 99K
(Policies)
39: R23 Accounts and Other Receivables, Net of Current HTML 32K
Expected Credit Losses (Tables)
40: R24 Inventory (Tables) HTML 34K
41: R25 Property, Plant and Equipment, Net of Accumulated HTML 52K
Depreciation (Tables)
42: R26 Derivative Instruments (Tables) HTML 113K
43: R27 Other Non-Current Assets, Net (Tables) HTML 36K
44: R28 Accrued Liabilities (Tables) HTML 33K
45: R29 Debt (Tables) HTML 88K
46: R30 Revenues from Contracts with Customers (Tables) HTML 69K
47: R31 Related Party Transactions (Tables) HTML 68K
48: R32 Commitments and Contingencies (Tables) HTML 34K
49: R33 Customer Concentration (Tables) HTML 58K
50: R34 Supplemental Cash Flow Information (Tables) HTML 33K
51: R35 Organization and Nature of Operations (Details) HTML 38K
52: R36 Summary of Significant Accounting Policies HTML 55K
(Details)
53: R37 Restricted Cash and Cash Equivalents (Details) HTML 29K
54: R38 Accounts and Other Receivables, Net of Current HTML 31K
Expected Credit Losses (Details)
55: R39 Inventory (Details) HTML 34K
56: R40 Property, Plant and Equipment, Net of Accumulated HTML 42K
Depreciation - Schedule of Property, Plant and
Equipment, Net of Accumulated Depreciation
(Details)
57: R41 Property, Plant and Equipment, Net of Accumulated HTML 28K
Depreciation - Schedule of Depreciation and
Offsets to LNG Terminal Costs (Details)
58: R42 Property, Plant and Equipment, Net of Accumulated HTML 37K
Depreciation - Estimated Useful Lives (Details)
59: R43 Derivative Instruments - Narrative (Details) HTML 34K
60: R44 Derivative Instruments - Fair Value of Derivative HTML 33K
Assets and Liabilities (Details)
61: R45 Derivative Instruments - Fair Value Inputs - HTML 40K
Quantitative Information (Details)
62: R46 Derivative Instruments - Schedule of Level 3 HTML 45K
Activity (Details)
63: R47 Derivative Instruments - Fair Value of Derivative HTML 57K
Instruments by Balance Sheet Location (Details)
64: R48 Derivative Instruments - Derivative Gain (Loss) HTML 34K
(Details)
65: R49 Derivative Instruments - Derivative Net HTML 43K
Presentation on Balance Sheets (Details)
66: R50 Other Non-Current Assets, Net (Details) HTML 36K
67: R51 Accrued Liabilities (Details) HTML 35K
68: R52 Debt - Schedule of Debt Instruments (Details) HTML 69K
69: R53 Debt - Schedule of Maturities (Details) HTML 43K
70: R54 Debt - Credit Facilities (Details) HTML 56K
71: R55 Debt - Interest Expense (Details) HTML 30K
72: R56 Debt - Schedule of Carrying Values and Estimated HTML 44K
Fair Values of Debt Instruments (Details)
73: R57 Revenues from Contracts with Customers - Narrative HTML 31K
(Details)
74: R58 Revenues from Contracts with Customers - Schedule HTML 52K
of Disaggregation of Revenue (Details)
75: R59 Revenues from Contracts with Customers - Contract HTML 39K
Assets and Liabilities (Details)
76: R60 Revenues from Contracts with Customers - Schedule HTML 42K
of Transaction Price Allocated to Future
Performance Obligations (Details)
77: R61 Related Party Transactions - Schedule of Related HTML 65K
Party Transactions (Details)
78: R62 Related Party Transactions - Narrative (Details) HTML 123K
79: R63 Commitments and Contingencies - Narrative HTML 43K
(Details)
80: R64 Commitments and Contingencies - Purchase HTML 40K
Obligations Table (Details)
81: R65 Customer Concentration - Schedule of Customer HTML 48K
Concentration (Details)
82: R66 Customer Concentration - Schedule of Revenues from HTML 48K
External Customers by Country (Details)
83: R67 Supplemental Cash Flow Information (Details) HTML 34K
86: XML IDEA XML File -- Filing Summary XML 152K
84: XML XBRL Instance -- spl-20211231_htm XML 2.06M
85: EXCEL IDEA Workbook of Financial Reports XLSX 101K
13: EX-101.CAL XBRL Calculations -- spl-20211231_cal XML 171K
14: EX-101.DEF XBRL Definitions -- spl-20211231_def XML 606K
15: EX-101.LAB XBRL Labels -- spl-20211231_lab XML 1.56M
16: EX-101.PRE XBRL Presentations -- spl-20211231_pre XML 919K
12: EX-101.SCH XBRL Schema -- spl-20211231 XSD 191K
87: JSON XBRL Instance as JSON Data -- MetaLinks 370± 529K
88: ZIP XBRL Zipped Folder -- 0001499200-22-000003-xbrl Zip 760K
The Agreement between the Parties listed above is changed as follows:
1.In
accordance with Section 6.1 of the Agreement (Change Orders Requested by Owner), the Parties agree this Change Order provides a credit to Company for unused costs associated with the permanent beam bridge at the existing north bridge location between 80 Acres and Lighthouse Road (“80 Acres Bridge”).
2.On 17 June 2021, the Parties executed Change Order No. CO-00047, dated 15 June 2021 for Contractor’s engineering, procurement and construction costs to install the 80 Acres Bridge, including demolition and removal of the existing north and south bridges currently in place.
3.On 28 September 2021, Contractor’s Bridge Supplier (Acrow Bridges) respectfully withdrew their intent to bid and declined the Work for reasons
stated in Exhibit C of this Change Order.
4.On 19 November 2021, Owner requested a credit for CO-00047, which is the purpose of this Change Order.
5.The Parties agree a separate and complete Change Order shall be prepared for the 80 Acres Bridge, which will be subject to separate review and approval.
6.The detailed cost breakdown for this Change Order is detailed in Exhibit A of this Change Order.
7.Schedule C-3 (Milestone Payment Schedule) of Attachment C of the Agreement will be amended by including the milestone(s) listed in Exhibit B of this Change Order.
Adjustment
to Contract Price Applicable to Subproject 6(a)
1.
The original Contract Price Applicable to Subproject 6(a) was
$
2,016,892,573
2.
Net change for Contract
Price Applicable to Subproject 6(a) by previously authorized Change Orders (#01-08, 10-13, 15, 17-18, 21-22, 24, 28-29, 31-32, 34-35, 38, 41-42, 45-49, 51, 53)
$
17,846,936
3.
The Contract Price Applicable to Subproject 6(a) prior to this Change Order was
$
2,034,739,509
4.
The Contract Price Applicable
to Subproject 6(a) will be decreased by this Change Order in the amount of
$
(914,941)
5.
The Provisional Sum Applicable to Subproject 6(a) will be unchanged by this Change Order in the amount of
$
—
6.
The Contract Price Applicable to Subproject 6(a) including this
Change Order will be
$
2,033,824,568
Adjustment to Contract Price Applicable to Subproject 6(b)
7.
The original Contract
Price Applicable to Subproject 6(b) (in CO-00009) was
$
457,696,000
8.
Net change for Contract Price Applicable to Subproject 6(b) by previously authorized Change Orders (#14, 16, 19-20, 23, 25-27, 30-31, 33, 36-37, 39-40, 43-44, 50, 52)
$
(3,978,536)
9.
The Contract Price Applicable to Subproject 6(b)
prior to this Change Order was
$
453,717,464
10.
The Contract Price Applicable to Subproject 6(b) will be unchanged by this Change Order
$
—
11.
The Provisional Sum Applicable to Subproject 6(b) will be unchanged by this Change Order
$
—
12.
The
Contract Price Applicable to Subproject 6(b) including this Change Order will be
The
original Contract Price for Subproject 6(a) and Subproject 6(b) was (add lines 1 and 7)
$
2,474,588,573
14.
The Contract Price prior to this Change Order was (add lines 3 and 9)
$
2,488,456,973
15.
The Contract
Price will be decreased by this Change Order in the amount of (add lines 4, 5, 10 and 11)
$
(914,941)
16.
The new Contract Price including this Change Order will be (add lines 14 and 15)
$
2,487,542,032
Adjustment to dates in Project Schedule for Subproject 6(a)
The
following dates are modified: N/A
Adjustment to other Changed Criteria for Subproject 6(a): N/A
Adjustment to Payment Schedule for Subproject 6(a): Yes; see Exhibit B
Adjustment to Minimum Acceptance Criteria for Subproject 6(a): N/A
Adjustment to Performance Guarantees for Subproject 6(a): N/A
Adjustment to Design Basis for Subproject 6(a): N/A
Other adjustments to liability or obligations of Contractor or Owner under the Agreement for Subproject 6(a): N/A
Adjustment
to dates in Project Schedule for Subproject 6(b)
The following dates are modified: N/A
Adjustment to other Changed Criteria for Subproject 6(b): N/A
Adjustment to Payment Schedule for Subproject 6(b): N/A
Adjustment to Design Basis for Subproject 6(b): N/A
Other adjustments to liability or obligation of Contractor or Owner under the Agreement: N/A
Select either A or B:
[A] This Change Order shall constitute a full and final settlement and accord and satisfaction of
all effects of the change reflected in this Change Order upon the Changed Criteria and shall be deemed to compensate Contractor fully for such change. Initials: /s/ KM Contractor /s/ DC Owner
[B] This Change Order shall not constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall not be deemed to compensate Contractor fully for such change. Initials: _____ Contractor _____ Owner
Upon execution of this Change Order by Owner and Contractor, the above-referenced change
shall become a valid and binding part of the original Agreement without exception or qualification, unless noted in this Change Order. Except as modified by this and any previously issued Change Orders, all other terms and conditions of the Agreement shall remain in full force and effect. This Change Order is executed by each of the Parties’ duly authorized representatives.
The Agreement between the Parties
listed above is changed as follows:
1.In accordance with Section 6.2 of the Agreement (Change Orders Requested by Contractor), the Parties agree this Change Order includes Contractor’s actual cost impacts to the Water Treatment Filter Washing Work due to the Change in Law of the Louisiana Pollutant Discharge Elimination System (LPDES) Permit No. LA0122441.
The revised LPDES Permit superseded the 2018 Louisiana Department of Environmental Quality (LDEQ) Permit,
thereby revising the total suspended solid (TSS) levels from 90 mg/L to 30mg/L, which required a substantial change
to Contractor’s execution of the Water Treatment Filter Washing Work. Refer to Exhibit
C for the timeline of events.
2.The detailed cost breakdown for this Change Order is detailed in Exhibit A of this Change Order.
3.Schedule C-3 (Milestone Payment Schedule) of Attachment C of the Agreement will be amended by including the milestone(s) listed in Exhibit B of this Change Order.
Adjustment to Contract Price Applicable to Subproject 6(a)
1.
The
original Contract Price Applicable to Subproject 6(a) was
$
2,016,892,573
2.
Net change for Contract Price Applicable to Subproject 6(a) by previously authorized Change Orders (#01-08, 10-13, 15, 17-18, 21-22, 24, 28-29, 31-32, 34-35, 38, 41-42, 45-49, 51, 53, 54)
$
16,931,995
3.
The Contract
Price Applicable to Subproject 6(a) prior to this Change Order was
$
2,033,824,568
4.
The Contract Price Applicable to Subproject 6(a) will be increased by this Change Order in the amount of
$
305,517
5.
The Provisional Sum Applicable to Subproject 6(a) will be unchanged by this Change Order in the amount of
$
—
6.
The
Contract Price Applicable to Subproject 6(a) including this Change Order will be
$
2,034,130,085
Adjustment to Contract Price Applicable to Subproject 6(b)
7.
The
original Contract Price Applicable to Subproject 6(b) (in CO-00009) was
$
457,696,000
8.
Net change for Contract Price Applicable to Subproject 6(b) by previously authorized Change Orders (#14, 16, 19-20, 23, 25-27, 30-31, 33, 36-37, 39-40, 43-44, 50, 52)
$
(3,978,536)
9.
The Contract
Price Applicable to Subproject 6(b) prior to this Change Order was
$
453,717,464
10.
The Contract Price Applicable to Subproject 6(b) will be unchanged by this Change Order
$
—
11.
The Provisional Sum Applicable to Subproject 6(b) will be unchanged by this Change Order
$
—
12.
The
Contract Price Applicable to Subproject 6(b) including this Change Order will be
The
original Contract Price for Subproject 6(a) and Subproject 6(b) was (add lines 1 and 7)
$
2,474,588,573
14.
The Contract Price prior to this Change Order was (add lines 3 and 9)
$
2,487,542,032
15.
The Contract
Price will be increased by this Change Order in the amount of (add lines 4, 5, 10 and 11)
$
305,517
16.
The new Contract Price including this Change Order will be (add lines 14 and 15)
$
2,487,847,549
Adjustment
to dates in Project Schedule for Subproject 6(a)
The following dates are modified : N/A
Adjustment to other Changed Criteria for Subproject 6(a): N/A
Adjustment to Payment Schedule for Subproject 6(a): Yes; see Exhibit B
Adjustment to Minimum Acceptance Criteria for Subproject 6(a): N/A
Adjustment to Performance Guarantees for Subproject 6(a): N/A
Adjustment to Design Basis for Subproject 6(a): N/A
Other adjustments to liability or obligations of Contractor or Owner under the Agreement
for Subproject 6(a): N/A
Adjustment to dates in Project Schedule for Subproject 6(b)
The following dates are modified: N/A
Adjustment to other Changed Criteria for Subproject 6(b): N/A
Adjustment to Payment Schedule for Subproject 6(b): N/A
Adjustment to Design Basis for Subproject 6(b): N/A
Other adjustments to liability or obligation of Contractor or Owner under the Agreement: N/A
Select either A or B:
[A] This Change Order shall constitute
a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall be deemed to compensate Contractor fully for such change. Initials: /s/ KM Contractor /s/ DC Owner
[B] This Change Order shall not constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall not be deemed to compensate Contractor fully for such change. Initials: ____ Contractor ____ Owner
Upon execution of this Change
Order by Owner and Contractor, the above-referenced change shall become a valid and binding part of the original Agreement without exception or qualification, unless noted in this Change Order. Except as modified by this and any previously issued Change Orders, all other terms and conditions of the Agreement shall remain in full force and effect. This Change Order is executed by each of the Parties’ duly authorized representatives.
The Agreement between the Parties
listed above is changed as follows:
1.In accordance with Section 6.2 of the Agreement (Change Orders Requested by Contractor), Parties agree this Change Order includes final and agreed-upon impacts to the Project caused by Hurricane Ida.
2.The detailed cost breakdown for this Change Order is detailed in Exhibit A of this Change Order.
3.Schedule C-3 (Milestone Payment Schedule) of Attachment C of the Agreement will be amended by including the milestone(s) listed in Exhibit B of this Change Order.
Adjustment
to Contract Price Applicable to Subproject 6(a)
1.
The original Contract Price Applicable to Subproject 6(a) was
$
2,016,892,573
2.
Net change for Contract
Price Applicable to Subproject 6(a) by previously authorized Change Orders (#01-08, 10-13, 15, 17-18, 21-22, 24, 28-29, 31-32, 34-35, 38, 41-42, 45-49, 51, 53-55)
$
17,237,512
3.
The Contract Price Applicable to Subproject 6(a) prior to this Change Order was
$
2,034,130,085
4.
The Contract Price Applicable
to Subproject 6(a) will be increased by this Change Order in the amount of
$
775,032
5.
The Provisional Sum Applicable to Subproject 6(a) will be unchanged by this Change Order in the amount of
$
—
6.
The Contract Price Applicable to Subproject 6(a) including this
Change Order will be
$
2,034,905,117
Adjustment to Contract Price Applicable to Subproject 6(b)
7.
The original Contract
Price Applicable to Subproject 6(b) (in CO-00009) was
$
457,696,000
8.
Net change for Contract Price Applicable to Subproject 6(b) by previously authorized Change Orders (#14, 16, 19-20, 23, 25-27, 30-31, 33, 36-37, 39-40, 43-44, 50, 52)
$
(3,978,536)
9.
The Contract Price Applicable to Subproject 6(b)
prior to this Change Order was
$
453,717,464
10.
The Contract Price Applicable to Subproject 6(b) will be unchanged by this Change Order
$
—
11.
The Provisional Sum Applicable to Subproject 6(b) will be unchanged by this Change Order
$
—
12.
The
Contract Price Applicable to Subproject 6(b) including this Change Order will be
The
original Contract Price for Subproject 6(a) and Subproject 6(b) was (add lines 1 and 7)
$
2,474,588,573
14.
The Contract Price prior to this Change Order was (add lines 3 and 9)....................................................
$
2,487,847,549
15.
The Contract
Price will be increased by this Change Order in the amount of (add lines 4, 5, 10 and 11)
$
775,032
16.
The new Contract Price including this Change Order will be (add lines 14 and 15)................................
$
2,488,622,581
Adjustment to dates in Project
Schedule for Subproject 6(a)
The following dates are modified: N/A
Adjustment to other Changed Criteria for Subproject 6(a): N/A
Adjustment to Payment Schedule for Subproject 6(a): Yes; see Exhibit B
Adjustment to Minimum Acceptance Criteria for Subproject 6(a): N/A
Adjustment to Performance Guarantees for Subproject 6(a): N/A
Adjustment to Design Basis for Subproject 6(a): N/A
Other
adjustments to liability or obligations of Contractor or Owner under the Agreement for Subproject 6(a): N/A
Adjustment to dates in Project Schedule for Subproject 6(b)
The following dates are modified: N/A
Adjustment to other Changed Criteria for Subproject 6(b): N/A
Adjustment to Payment Schedule for Subproject 6(b): N/A
Adjustment to Design Basis for Subproject 6(b): N/A
Other adjustments to liability or obligation of Contractor or Owner under the Agreement: N/A
Select either A or B:
[A]
This Change Order shall constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall be deemed to compensate Contractor fully for such change. Initials: /s/ KM Contractor /s/ DC Owner
[B] This Change Order shall not constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall not be deemed to compensate Contractor fully for such change. Initials: ____ Contractor ____ Owner
Upon
execution of this Change Order by Owner and Contractor, the above-referenced change shall become a valid and binding part of the original Agreement without exception or qualification, unless noted in this Change Order. Except as modified by this and any previously issued Change Orders, all other terms and conditions of the Agreement shall remain in full force and effect. This Change Order is executed by each of the Parties’ duly authorized representatives.
The Agreement between the Parties
listed above is changed as follows:
1.In accordance with Section 6.2 of the Agreement (Change Orders Requested by Contractor), Parties agree this Change Order includes final and agreed-upon impacts to the Project caused by Hurricane Nicholas.
2. The detailed cost breakdown for this Change Order is detailed in Exhibit A of this Change Order.
3. Schedule C-3 (Milestone Payment Schedule) of Attachment C of the Agreement will be amended by including the milestone(s) listed in Exhibit B of this Change Order.
Adjustment
to Contract Price Applicable to Subproject 6(a)
1.
The original Contract Price Applicable to Subproject 6(a) was
$
2,016,892,573
2.
Net change for Contract
Price Applicable to Subproject 6(a) by previously authorized Change Orders (#01-08, 10-13, 15, 17-18, 21-22, 24, 28-29, 31-32, 34-35, 38, 41-42, 45-49, 51, 53-56)
$
18,012,544
3.
The Contract Price Applicable to Subproject 6(a) prior to this Change Order was
$
2,034,905,117
4.
The Contract Price Applicable
to Subproject 6(a) will be increased by this Change Order in the amount of
$
98,631
5.
The Provisional Sum Applicable to Subproject 6(a) will be unchanged by this Change Order in the amount of
$
—
6.
The Contract Price Applicable to Subproject 6(a) including this
Change Order will be
$
2,035,003,748
Adjustment to Contract Price Applicable to Subproject 6(b)
7.
The original Contract
Price Applicable to Subproject 6(b) (in CO-00009) was
$
457,696,000
8.
Net change for Contract Price Applicable to Subproject 6(b) by previously authorized Change Orders (#14, 16, 19-20, 23, 25-27, 30-31, 33, 36-37, 39-40, 43-44, 50, 52)
$
(3,978,536)
9.
The Contract Price Applicable to Subproject 6(b)
prior to this Change Order was
$
453,717,464
10.
The Contract Price Applicable to Subproject 6(b) will be unchanged by this Change Order
$
—
11.
The Provisional Sum Applicable to Subproject 6(b) will be unchanged by this Change Order
$
—
12.
The
Contract Price Applicable to Subproject 6(b) including this Change Order will be
The
original Contract Price for Subproject 6(a) and Subproject 6(b) was (add lines 1 and 7)
$
2,474,588,573
14.
The Contract Price prior to this Change Order was (add lines 3 and 9)....................................................
$
2,488,622,581
15.
The Contract
Price will be increased by this Change Order in the amount of (add lines 4, 5, 10 and 11)
$
98,631
16.
The new Contract Price including this Change Order will be (add lines 14 and 15)................................
$
2,488,721,212
Adjustment to dates in Project Schedule
for Subproject 6(a)
The following dates are modified: N/A
Adjustment to other Changed Criteria for Subproject 6(a): N/A
Adjustment to Payment Schedule for Subproject 6(a): Yes; see Exhibit B
Adjustment to Minimum Acceptance Criteria for Subproject 6(a): N/A
Adjustment to Performance Guarantees for Subproject 6(a): N/A
Adjustment to Design Basis for Subproject 6(a): N/A
Other adjustments
to liability or obligations of Contractor or Owner under the Agreement for Subproject 6(a): N/A
Adjustment to dates in Project Schedule for Subproject 6(b)
The following dates are modified: N/A
Adjustment to other Changed Criteria for Subproject 6(b): N/A
Adjustment to Payment Schedule for Subproject 6(b): N/A
Adjustment to Design Basis for Subproject 6(b): N/A
Other adjustments to liability or obligation of Contractor or Owner under the Agreement: N/A
Select either A or B:
[A]
This Change Order shall constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall be deemed to compensate Contractor fully for such change. Initials: /s/ KM Contractor /s/ DC Owner
[B] This Change Order shall not constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall not be deemed to compensate Contractor fully for such change. Initials: ____ Contractor ____ Owner
Upon
execution of this Change Order by Owner and Contractor, the above-referenced change shall become a valid and binding part of the original Agreement without exception or qualification, unless noted in this Change Order. Except as modified by this and any previously issued Change Orders, all other terms and conditions of the Agreement shall remain in full force and effect. This Change Order is executed by each of the Parties’ duly authorized representatives.